Stage 1 of Central Coast Quarter, The Waterfront, reaches 50% completion milestone

Stage 1 of Central Coast Quarter, The Waterfront, is forging ahead—nearing the 50% completion milestone, all thanks to the unwavering dedication of our Urban construction team!
Our progress has soared up to Level 22, marking a significant achievement as we begin work on the communal Panorama Deck. Meanwhile, scaffolding is coming down to showcase the striking louvre façade from the Ground Floor through Level 6. Inside, we’re moving full steam ahead: walls, ceilings, and windows are completed up to Level 6, joinery is done through Level 2, tiling has started, and fit-outs in the lower-level apartments are well underway.
Looking ahead, we’re on schedule for completion of the structure in Febuary.